It’s a Plan

Scrum vs Kanban: How to Choose by the Way Work Reaches Your Team

Choose between Scrum and Kanban by how work reaches your team: in planned batches or as a steady stream. See one board set up both ways, what each method does with an urgent request mid-sprint, and how to switch without losing history.

Andrii PoluosmakUpdated 9 min read

The Scrum vs Kanban choice depends on how work reaches your team. Use Scrum if you can plan that work in batches: you set a goal for the next sprint and select the items behind it. If it comes in a steady stream you can't predict, use Kanban, where you limit the work in progress (WIP) and pull the next item when you have room.

Planned batches or a steady stream?

List the items your team finished last month and mark each one: planned if you chose it ahead of time, unplanned if it arrived and you had to start it. Lean toward Scrum if you planned most of them and toward Kanban if most arrived unplanned.

In a 2012 IEEE Software study, Sjøberg, Johnsen and Solberg recommend that software companies consider Kanban if they struggle with effort estimation and with "interruptions caused by ad hoc bug fixing, support, and maintenance tasks." Kanban's application "is not limited to any specific industry or context," according to the May 2025 Kanban Guide. If you work outside software, apply the same test to briefs, requests or tickets.

Kanban vs Scrum side by side

The difference between Scrum and Kanban is what you control: the length and goal of a sprint in Scrum, the amount of work in progress in Kanban. The 2020 Scrum Guide, Scrum.org's glossary, the Kanban Guide and Savita Pahuja's post on Agile Alliance's community blog describe the two methods in these terms:

What differsScrumKanban
CadenceSprints of one month or less, back to backContinuous, with no sprint end
RolesScrum Master, Product Owner and DevelopersKanban system members: those who take part in value delivery
CommitmentThe Sprint Goal, with flexible work behind itA forecast instead, the service level expectation (SLE)
Change during the cycleAllowed unless it endangers the Sprint GoalAllowed in the queues at any time
MetricsVelocity and burndown, both optionalWIP, throughput, work item age and cycle time, all mandatory

In the glossary, velocity indicates how much Product Backlog a team turns into an Increment in a sprint, and a burndown chart shows the work thought to remain in a backlog. The Kanban Guide defines cycle time as "the elapsed time between when a work item started and when a work item finished." For lead time, agree with your team which columns start and stop the clock. The IEEE Software authors count from "next" to "ready for release."

Is Kanban agile?

Yes, and so is Scrum. Kniberg and Skarin count both methods as Lean and Agile, according to an Elsevier paper on Scrum and Kanban in software projects. If your company asks for agile, you can use either.

Which one is faster?

Don't expect the switch by itself to speed you up. The IEEE Software study covers more than 12,000 work items from one company that switched from Scrum to Kanban in 2010. The company's average lead time for bugs was 12 days in Scrum and 5 in Kanban, but counting from 2010 it was 4.7 days in Scrum and 5.4 in Kanban.

Average lead time for bugs at one software company, in days

Source: IEEE Software, Quantifying the Effect of Using Kanban versus Scrum

Average lead time for bugs at one software company, in days
Scrum, overall12
Scrum, from 20104.7
Kanban, from 20105.4

Scrum board vs Kanban board: one board set up both ways

Take a board with the columns To do, In progress, Review and Done. Keep the columns and change how cards enter and leave.

Board ruleSet up for ScrumSet up for Kanban
To do holdsThe Sprint Backlog: items selected for the Sprint GoalThe next items in order, changed at any time
In progress and Review holdCards from the Sprint BacklogCards up to the WIP limit of each column
A card entersIn Sprint Planning, or later if the Sprint Goal stays safeWhen there is a clear signal of capacity
When the sprint endsUnfinished cards return to the Product Backlog and a new sprint startsNothing, because there is no sprint

Scrum.org's glossary calls Scrum boards "an optional implementation within Scrum," and the Scrum Guide doesn't tell you to reset one each sprint. The Kanban Guide tells you to control WIP, and you can make that visible with a limit on each column.

To start each sprint with a fresh board, filter yours by the current sprint. In It's a Plan, a saved view filtered by Active cycle switches to each new sprint.

The same four-column board is shown twice: the Scrum board has a Sprint Goal above it and two unfinished cards going down to a row of backlog cards, and the Kanban board has a WIP limit over its two middle columns and cards moving from column to column.

An urgent request lands mid-sprint

Say it's day four of a two-week sprint and your whole team is busy. Then a bug comes in that hurts your customers.

What Scrum does

The Scrum Guide allows no changes "that would endanger the Sprint Goal," but scope "may be clarified and renegotiated with the Product Owner as more is learned." The Scrum.org post Scrum is Not an Excuse to Ignore Emergencies gives the Product Owner three options:

  1. Postpone it. Put it in the Product Backlog if it can wait for the next sprint.
  2. Add it to the sprint. This "could result in removing lower-priority work from the Sprint," so name the card you take out.
  3. Cancel the sprint. The Scrum Guide allows this if the Sprint Goal becomes obsolete, and only the Product Owner can do it.

If you get frequent emergencies, the post says, use the Retrospective to find ways to reduce them.

What Kanban does

You have no sprint to protect, so you decide whether the card may enter a full column. The Kanban Guide says acceptable exceptions to controlling WIP "should be made explicit" in your Definition of Workflow. Write yours before the next emergency:

  1. Pull it next if you have room.
  2. Breach the limit and record it if the column is full. "It is better to breach your WIP limits by exception," the Scrum.org post Classes of Service in Kanban says. If you raise the limit instead, it warns, "we are actually increasing our WIP as standard."
  3. If you add an Expedite class, keep it for work that is "really urgent." Once you give some items priority, some age more than others, the post says, "eventually leading to unpredictable cycle times."

If you allow recorded breaches, use a limit that warns you. In It's a Plan, a soft WIP limit marks a column full, and a hard limit blocks the move.

An urgent card branches to Scrum, where the Product Owner can postpone it to the backlog, add it and take another card out or cancel the sprint, and to Kanban, where it enters a free slot or is recorded over the limit of a full column.

A 5-question Scrum vs Kanban check

Answer for one team at a time:

QuestionScrumKanban
1. Can you list most of the next sprint's work today?YesNo, it arrives as you go
2. Can most urgent requests wait for the next sprint?YesNo
3. Does one goal cover most of the work?YesNo, the requests are unrelated
4. Can you estimate well enough to fill a sprint?YesNo
5. Do you have a Product Owner and a Scrum Master?YesNo

Go with the side that gets most of your answers. If your answers to 1 and 2 both point the other way, follow them, because they describe how work arrives.

When Scrumban makes sense

Mix the two if you can plan part of your work and the rest keeps interrupting you. Pahuja suggests Scrumban for "projects with frequent and unexpected user stories or programming errors." Plan at regular intervals, but only "to fill the slots available," and watch cycle time more than burndown. Tell your stakeholders which parts of Scrum you dropped, because the Scrum Guide says that with only parts of it in place, "the result is not Scrum."

How to switch without losing history or momentum

  1. Stay in one tracker. Keep your old and new work in one project. The IEEE Software authors compared both methods with three years of data from one system.
  2. Record a baseline. Save your recent velocity, lead time and cycle time for each type of work.
  3. Close the last sprint. Send unfinished cards back to the queue. In It's a Plan, finished issues stay on the old sprint.
  4. Start with one team. At the company in the study, some teams still used Scrum while others had switched.
  5. Keep the meetings that help. That company kept daily standups, replaced sprint demos with status meetings once or twice a week, and abandoned start-up meetings focused on estimates.
  6. Forecast with a guess, then correct it. The Kanban Guide's sample SLE is "85% of work items will be finished in eight days or less." If you have no cycle time history, it says, "a best guess will do" until you have enough data.

To move from Kanban to Scrum, choose a sprint length, write a Sprint Goal and select items for it from your queue. The Scrum Guide limits Sprint Planning to eight hours for a one-month Sprint.

Start with last month's work

Mark last month's items, answer the five questions and write your rule for urgent requests. Then set up your board in It's a Plan. Use cycles for Scrum sprints or WIP limits on columns for Kanban, and switch later in the same project.

Key takeaway

Choose Scrum when you can plan your work in batches and Kanban when it arrives as a steady stream. When an urgent request lands mid-sprint, a Scrum Product Owner can postpone it, add it or cancel the sprint, while a Kanban team follows its written exceptions to the WIP limit. Record your cycle time by work type before you switch, so you can compare it later.

Andrii Poluosmak

Founder

Andrii founded It’s a Plan and leads its product and roadmap, from the open-source edition to Pro for teams. He works with the project’s contributors and the teams that run It’s a Plan.