It’s a Plan

Project Planning Template: 8 Sections to Fill In, With a Worked Example

The 8 sections of a project planning template and the question each one answers, filled in for a 10-week website relaunch. It also covers what a 2-week project can skip, when to use Excel, a doc or a project tool, and how to run a weekly plan review.

Andrii PoluosmakUpdated 13 min read

A project planning template gives each project the same 8 questions to answer before work starts: why the project exists, what is in and out of scope, what gets delivered, who does each task, when the milestones fall, what depends on what, what could go wrong, and who hears about progress. Write the answers down and you hear the team's disagreements at kickoff instead of halfway through.

Then you have to keep the plan tied to the work. In a PMI survey of 300 senior executives, 35% named a disconnect between planning and execution as their top barrier to reinvention, more than any other factor. Copy the 8 sections below into a doc, a spreadsheet or a project tool, and model yours on the website relaunch example. Then review the plan every week.

The 8 sections a project planning template needs

Each section answers one question. If a section has no answer yet, you have an open decision: give it an owner and a date.

#SectionThe question it answers
1GoalWhy are we doing this, and how will we know it worked?
2ScopeWhat is included, and what is left out on purpose?
3DeliverablesWhat will we hand over at the end?
4Tasks and ownersWhat work produces each deliverable, and who owns each piece?
5MilestonesWhich checkpoints show we are on track, and when?
6DependenciesWhat has to finish before something else can start?
7RisksWhat could go wrong, and what will we do if it does?
8CommunicationWho needs to hear what, how often, and from whom?

These sections cover most of what APM, the UK's Association for Project Management, includes in its definition of integrated planning: benefits, success criteria, scope, quality, time, resources, cost, risk and communications. Add a Budget or Quality section if your project needs one.

In Wellingtone's State of Project Management Survey 2018, which covered more than 300 UK organisations, 59% of respondents mostly or always created a scoping document and 48% mostly or always baselined their schedules, while 62% did risk management. Fill in all 8 sections before kickoff, even if some answers are a single line.

Planning basics in a UK survey of 300+ organisations

Source: Wellingtone, The State of Project Management Survey 2018

Planning basics in a UK survey of 300+ organisations
Scoping document (mostly or always)59%
Baselined schedule (mostly or always)48%
Risk management62%

Two pairs of sections are easy to confuse:

  • Milestone vs deliverable. A deliverable is something you hand over, such as a design file. A milestone is a date on which the team finishes something and checks it, such as "design approved". APM describes phases and intermediate deliverables as a mechanism for arranging milestones and project reviews. End each phase with a milestone at which you review its deliverable.
  • Dependency vs risk. A dependency is certain: the developer cannot build pages before the sponsor approves the design. A risk is uncertain: the approval might come late. Put the first in section 6 and the second in section 7.

The template filled in for a website relaunch

In the sample project, a small company relaunches its marketing website in 10 weeks, with a new design, rewritten key pages and a new content management system (CMS).

1. Goal

Write the purpose, one to three measures of success, and the sponsor who signs off.

  • Purpose: a site the marketing team can update without a developer.
  • Success measures: the site is live by the end of week 10; the marketing team publishes a new page without help; demo requests from the site stay at least at today's monthly level.
  • Sponsor: Head of Marketing.

In PMI's Pulse of the Profession 2026, 39% of high performers established a shared understanding of what success looks like with the sponsor before execution began, against 30% of low performers. Get the sponsor to approve the success measures before the first task starts.

Practitioners who align with the sponsor on success before execution

Source: PMI, Pulse of the Profession 2026

Practitioners who align with the sponsor on success before execution
High performers39%
Low performers30%

2. Scope

List what is in, then what is out.

  • In scope: a new design for all page types; rewritten home, pricing and product pages; existing blog posts moved to the new CMS; redirects from old URLs.
  • Out of scope: new blog posts; a customer login area; translations; a new brand identity.

PMI's Pulse of the Profession 2018 found that 52% of projects completed in the previous 12 months had scope creep or uncontrolled changes to scope, up from 43% five years earlier. In the same PMI article, Monica Sacco of IBM advises identifying what is outside the scope during planning, too. Check each new request against your out-of-scope list, and send the sponsor any request that appears on it as a change decision.

3. Deliverables

List what you hand over, and make each item something a person can approve: the sitemap, approved page designs, rewritten key pages, the tested site on the new CMS, a redirect map and a one-page guide to editing pages.

4. Tasks and owners

Give each task one owner, a person rather than a team, and a due date. Keep tasks small enough to track week by week. McKinsey describes one high-tech company that required teams to break all activities down so that each needed fewer than 20 person-days and took no longer than four weeks. Set a size limit for your team and split any task above it.

TaskOwnerDue
Write the sitemap and page listMarketing leadWeek 1
Design the page typesDesignerWeek 3
Set up the CMSDeveloperWeek 4
Rewrite the key pagesCopywriterWeek 5
Build the pages in the CMSDeveloperWeek 7
Move blog posts and set redirectsDeveloperWeek 8
Test and launchMarketing leadWeek 10

5. Milestones

Give each milestone a week and a check that proves it happened.

MilestoneWeekHow it is checked
Sitemap approved1The sponsor signs off the page list
Design approved3The sponsor approves every page type
Ready for testing8All pages built, redirects in place
Launch10The site is live and old URLs redirect

Track each milestone through the tasks under it. In It's a Plan, an initiative holds a target date and the issues under it. It turns At risk when work falls 10% behind the time gone, without anyone posting a status update.

6. Dependencies

Write each dependency as "X waits for Y", and mark the ones outside the team.

TaskWaits forOutside the team?
Build the pagesDesign approvedNo
Rewrite the key pagesSitemap approvedNo
Move blog postsCMS set upNo
LaunchDNS change by ITYes

PMI's Pulse of the Profession 2026 found that one in five practitioners use scenario planning, which includes mapping interdependencies and anticipating disruption early. Before kickoff, go through each row and ask what happens to the launch date if Y is a week late.

7. Risks

Write each risk with its likelihood, impact, response and owner.

RiskLikelihoodImpactResponseOwner
Design feedback comes lateMediumHighBook review slots at kickoffMarketing lead
Blog posts import badlyMediumMediumTest-import a few posts in week 4Developer
New requests arrive mid-projectHighHighCheck the out-of-scope list; the sponsor decidesMarketing lead

The same PMI article quotes IBM's advice to "build a strong contingency budget to limit the negative impact of unexpected problems." Keep a reserve of time and money in the plan, and name the person who can release it.

8. Communication

Write who gets which update, when, and from whom.

AudienceWhat they hearWhenFrom
SponsorProgress, decisions needed, top risksWeekly callMarketing lead
Sales and supportLaunch date and what changes for customersWeeks 3, 8 and 10Marketing lead
ITThe DNS change dateWeek 8 and launch dayDeveloper

PMI's 2013 report The High Cost of Low Performance found that US$135 million is at risk for every US$1 billion spent on projects, and that 56% of it, US$75 million, is at risk because of ineffective communications. In the same study, high performers created formal communications plans for nearly twice as many projects as low performers. Write yours down, even if it has three rows.

A one-page plan titled Website Relaunch with eight section cards in two rows, and below them a timeline with four milestone markers, of which "Design approved" is labelled and the final "Launch" marker is highlighted.

Simple project plan template vs full plan: what a 2-week project can skip

A 2-week project needs the same answers in shorter form. In a simple project plan template, you keep the goal, scope, tasks and owners in full and fold the other sections into them.

Section2-week projectMulti-month project
GoalOne sentence and the sponsorPurpose, success measures, sponsor sign-off
ScopeA few lines in and outIn and out lists, plus how changes are decided
DeliverablesMerged into the task listA separate list
Tasks and ownersFull list with owners and datesFull list, grouped by phase
MilestonesThe end dateOne per phase, each with a review
DependenciesA note in the task rowA separate table, outside ones marked
RisksThe top 2 or 3 in one paragraphA risk table with owners and a reserve
CommunicationOne line: who gets updates, and whenA table by audience

For a long project, a project management plan template adds sections for budget, quality and resources, which APM also counts as part of planning.

If your team works in sprints, you still need the plan. APM's guidance on planning states that "when using an iterative life cycle approach, a baseline plan is still required". Keep the goal, scope, milestones and risks in the plan, and the detailed tasks in the sprint backlog.

Project plan template: Excel, doc or project tool?

Each format works until the plan changes every week and several people update it.

FormatWorks whenBreaks when
SpreadsheetOne person edits it, and you need sums or simple date mathsSeveral people edit it, or one slipped date has to move every task after it
DocThe plan is mostly text: goal, scope, risks, communicationTask status changes daily, and nobody knows which copy is current
Project toolTasks have owners, due dates and dependencies, and status changes oftenNobody updates it, or the goal and scope live somewhere else

Raymond Panko of the University of Hawaii reviewed field audits of real spreadsheets, mostly financial models. The audits that used better methods found errors in at least 86% of the spreadsheets they checked. Users often type a value over a formula cell, and one survey of an Australian mining company's spreadsheets found this in about 30% of them. If you keep a project plan template in Excel, protect the formula cells and name one editor.

Wellingtone's 2018 survey found that 22% of organisations used PPM or resource-management software, and that many still collated reports by hand. A free project plan template gives you the columns; decide at kickoff who keeps them up to date.

You can keep the text sections in a doc and the tasks in a tool. In It's a Plan, Docs sit in the same project as the issues: type an issue number on the plan page to show its title and state, or select a line of text to turn it into an issue.

Keep the plan current with a weekly review

Keep the plan matched to the work: give it one owner, usually the project manager, and review it with the team every week.

Wellingtone's 10th State of Project Management Report, released in March 2026, found that 36% of organisations mostly or always complete projects on time. It also found that 72% of project professionals spend half a day or more each month collating reports. PMI's Step Up research names "relentlessly reassess to anticipate change and continuously adjust" as one of four elements of project success. Its Net Project Success Score was 27 when professionals used none of the four elements and 94 when they consistently applied all four, and 7% of professionals used all four.

Run the review in the same order each week:

  1. Tasks: mark what is done, update dates, and reassign tasks whose owner is away.
  2. Milestones: if the next one will slip, tell the sponsor this week.
  3. Dependencies: chase what is waiting, the outside ones first.
  4. Risks: close old ones, add new ones, and check that each response is under way.
  5. Scope: log new requests and the decision on each.
  6. Communication: send the sponsor update from the review notes.

Take the numbers for the update from the task list instead of retyping them. In It's a Plan, dashboards count the issues when you open them, and the Burnup widget projects the finish date from the pace of recent weeks.

Copy the template and start your plan

Paste this blank version into a doc or spreadsheet, fill in each section for your project, and book the first weekly review before kickoff.

PROJECT PLAN: [project name]
Plan owner: [name]   Sponsor: [name]   Last reviewed: [date]

1. Goal: purpose | success measures | sponsor
2. Scope: in scope | out of scope
3. Deliverables: what you hand over
4. Tasks and owners: task | owner | due date
5. Milestones: milestone | date | how it is checked
6. Dependencies: task | waits for | outside the team?
7. Risks: risk | likelihood | impact | response | owner
8. Communication: audience | what they hear | when | from

If you plan in It's a Plan, save the setup as a project template, so the next project starts with the same workflow states, issue types, labels, fields and views. Then turn each task row into an issue with an owner and a due date.

Key takeaway

A project plan answers 8 questions before work starts: goal, scope, deliverables, tasks and owners, milestones, dependencies, risks and communication. Fill in every section, even with a single line, put an out-of-scope list next to the scope, give each task one owner and a due date, and have one plan owner review the plan with the team every week so it stays tied to the work.

Andrii Poluosmak

Founder

Andrii founded It’s a Plan and leads its product and roadmap, from the open-source edition to Pro for teams. He works with the project’s contributors and the teams that run It’s a Plan.

All posts by Andrii Poluosmak