A project planning template gives each project the same 8 questions to answer before work starts: why the project exists, what is in and out of scope, what gets delivered, who does each task, when the milestones fall, what depends on what, what could go wrong, and who hears about progress. Write the answers down and you hear the team's disagreements at kickoff instead of halfway through.
Then you have to keep the plan tied to the work. In a PMI survey of 300 senior executives, 35% named a disconnect between planning and execution as their top barrier to reinvention, more than any other factor. Copy the 8 sections below into a doc, a spreadsheet or a project tool, and model yours on the website relaunch example. Then review the plan every week.
The 8 sections a project planning template needs
Each section answers one question. If a section has no answer yet, you have an open decision: give it an owner and a date.
| # | Section | The question it answers |
|---|---|---|
| 1 | Goal | Why are we doing this, and how will we know it worked? |
| 2 | Scope | What is included, and what is left out on purpose? |
| 3 | Deliverables | What will we hand over at the end? |
| 4 | Tasks and owners | What work produces each deliverable, and who owns each piece? |
| 5 | Milestones | Which checkpoints show we are on track, and when? |
| 6 | Dependencies | What has to finish before something else can start? |
| 7 | Risks | What could go wrong, and what will we do if it does? |
| 8 | Communication | Who needs to hear what, how often, and from whom? |
These sections cover most of what APM, the UK's Association for Project Management, includes in its definition of integrated planning: benefits, success criteria, scope, quality, time, resources, cost, risk and communications. Add a Budget or Quality section if your project needs one.
In Wellingtone's State of Project Management Survey 2018, which covered more than 300 UK organisations, 59% of respondents mostly or always created a scoping document and 48% mostly or always baselined their schedules, while 62% did risk management. Fill in all 8 sections before kickoff, even if some answers are a single line.
| Scoping document (mostly or always) | 59% |
|---|---|
| Baselined schedule (mostly or always) | 48% |
| Risk management | 62% |
Two pairs of sections are easy to confuse:
- Milestone vs deliverable. A deliverable is something you hand over, such as a design file. A milestone is a date on which the team finishes something and checks it, such as "design approved". APM describes phases and intermediate deliverables as a mechanism for arranging milestones and project reviews. End each phase with a milestone at which you review its deliverable.
- Dependency vs risk. A dependency is certain: the developer cannot build pages before the sponsor approves the design. A risk is uncertain: the approval might come late. Put the first in section 6 and the second in section 7.
The template filled in for a website relaunch
In the sample project, a small company relaunches its marketing website in 10 weeks, with a new design, rewritten key pages and a new content management system (CMS).
1. Goal
Write the purpose, one to three measures of success, and the sponsor who signs off.
- Purpose: a site the marketing team can update without a developer.
- Success measures: the site is live by the end of week 10; the marketing team publishes a new page without help; demo requests from the site stay at least at today's monthly level.
- Sponsor: Head of Marketing.
In PMI's Pulse of the Profession 2026, 39% of high performers established a shared understanding of what success looks like with the sponsor before execution began, against 30% of low performers. Get the sponsor to approve the success measures before the first task starts.
| High performers | 39% |
|---|---|
| Low performers | 30% |
2. Scope
List what is in, then what is out.
- In scope: a new design for all page types; rewritten home, pricing and product pages; existing blog posts moved to the new CMS; redirects from old URLs.
- Out of scope: new blog posts; a customer login area; translations; a new brand identity.
PMI's Pulse of the Profession 2018 found that 52% of projects completed in the previous 12 months had scope creep or uncontrolled changes to scope, up from 43% five years earlier. In the same PMI article, Monica Sacco of IBM advises identifying what is outside the scope during planning, too. Check each new request against your out-of-scope list, and send the sponsor any request that appears on it as a change decision.
3. Deliverables
List what you hand over, and make each item something a person can approve: the sitemap, approved page designs, rewritten key pages, the tested site on the new CMS, a redirect map and a one-page guide to editing pages.
4. Tasks and owners
Give each task one owner, a person rather than a team, and a due date. Keep tasks small enough to track week by week. McKinsey describes one high-tech company that required teams to break all activities down so that each needed fewer than 20 person-days and took no longer than four weeks. Set a size limit for your team and split any task above it.
| Task | Owner | Due |
|---|---|---|
| Write the sitemap and page list | Marketing lead | Week 1 |
| Design the page types | Designer | Week 3 |
| Set up the CMS | Developer | Week 4 |
| Rewrite the key pages | Copywriter | Week 5 |
| Build the pages in the CMS | Developer | Week 7 |
| Move blog posts and set redirects | Developer | Week 8 |
| Test and launch | Marketing lead | Week 10 |
5. Milestones
Give each milestone a week and a check that proves it happened.
| Milestone | Week | How it is checked |
|---|---|---|
| Sitemap approved | 1 | The sponsor signs off the page list |
| Design approved | 3 | The sponsor approves every page type |
| Ready for testing | 8 | All pages built, redirects in place |
| Launch | 10 | The site is live and old URLs redirect |
Track each milestone through the tasks under it. In It's a Plan, an initiative holds a target date and the issues under it. It turns At risk when work falls 10% behind the time gone, without anyone posting a status update.
6. Dependencies
Write each dependency as "X waits for Y", and mark the ones outside the team.
| Task | Waits for | Outside the team? |
|---|---|---|
| Build the pages | Design approved | No |
| Rewrite the key pages | Sitemap approved | No |
| Move blog posts | CMS set up | No |
| Launch | DNS change by IT | Yes |
PMI's Pulse of the Profession 2026 found that one in five practitioners use scenario planning, which includes mapping interdependencies and anticipating disruption early. Before kickoff, go through each row and ask what happens to the launch date if Y is a week late.
7. Risks
Write each risk with its likelihood, impact, response and owner.
| Risk | Likelihood | Impact | Response | Owner |
|---|---|---|---|---|
| Design feedback comes late | Medium | High | Book review slots at kickoff | Marketing lead |
| Blog posts import badly | Medium | Medium | Test-import a few posts in week 4 | Developer |
| New requests arrive mid-project | High | High | Check the out-of-scope list; the sponsor decides | Marketing lead |
The same PMI article quotes IBM's advice to "build a strong contingency budget to limit the negative impact of unexpected problems." Keep a reserve of time and money in the plan, and name the person who can release it.
8. Communication
Write who gets which update, when, and from whom.
| Audience | What they hear | When | From |
|---|---|---|---|
| Sponsor | Progress, decisions needed, top risks | Weekly call | Marketing lead |
| Sales and support | Launch date and what changes for customers | Weeks 3, 8 and 10 | Marketing lead |
| IT | The DNS change date | Week 8 and launch day | Developer |
PMI's 2013 report The High Cost of Low Performance found that US$135 million is at risk for every US$1 billion spent on projects, and that 56% of it, US$75 million, is at risk because of ineffective communications. In the same study, high performers created formal communications plans for nearly twice as many projects as low performers. Write yours down, even if it has three rows.
Simple project plan template vs full plan: what a 2-week project can skip
A 2-week project needs the same answers in shorter form. In a simple project plan template, you keep the goal, scope, tasks and owners in full and fold the other sections into them.
| Section | 2-week project | Multi-month project |
|---|---|---|
| Goal | One sentence and the sponsor | Purpose, success measures, sponsor sign-off |
| Scope | A few lines in and out | In and out lists, plus how changes are decided |
| Deliverables | Merged into the task list | A separate list |
| Tasks and owners | Full list with owners and dates | Full list, grouped by phase |
| Milestones | The end date | One per phase, each with a review |
| Dependencies | A note in the task row | A separate table, outside ones marked |
| Risks | The top 2 or 3 in one paragraph | A risk table with owners and a reserve |
| Communication | One line: who gets updates, and when | A table by audience |
For a long project, a project management plan template adds sections for budget, quality and resources, which APM also counts as part of planning.
If your team works in sprints, you still need the plan. APM's guidance on planning states that "when using an iterative life cycle approach, a baseline plan is still required". Keep the goal, scope, milestones and risks in the plan, and the detailed tasks in the sprint backlog.
Project plan template: Excel, doc or project tool?
Each format works until the plan changes every week and several people update it.
| Format | Works when | Breaks when |
|---|---|---|
| Spreadsheet | One person edits it, and you need sums or simple date maths | Several people edit it, or one slipped date has to move every task after it |
| Doc | The plan is mostly text: goal, scope, risks, communication | Task status changes daily, and nobody knows which copy is current |
| Project tool | Tasks have owners, due dates and dependencies, and status changes often | Nobody updates it, or the goal and scope live somewhere else |
Raymond Panko of the University of Hawaii reviewed field audits of real spreadsheets, mostly financial models. The audits that used better methods found errors in at least 86% of the spreadsheets they checked. Users often type a value over a formula cell, and one survey of an Australian mining company's spreadsheets found this in about 30% of them. If you keep a project plan template in Excel, protect the formula cells and name one editor.
Wellingtone's 2018 survey found that 22% of organisations used PPM or resource-management software, and that many still collated reports by hand. A free project plan template gives you the columns; decide at kickoff who keeps them up to date.
You can keep the text sections in a doc and the tasks in a tool. In It's a Plan, Docs sit in the same project as the issues: type an issue number on the plan page to show its title and state, or select a line of text to turn it into an issue.
Keep the plan current with a weekly review
Keep the plan matched to the work: give it one owner, usually the project manager, and review it with the team every week.
Wellingtone's 10th State of Project Management Report, released in March 2026, found that 36% of organisations mostly or always complete projects on time. It also found that 72% of project professionals spend half a day or more each month collating reports. PMI's Step Up research names "relentlessly reassess to anticipate change and continuously adjust" as one of four elements of project success. Its Net Project Success Score was 27 when professionals used none of the four elements and 94 when they consistently applied all four, and 7% of professionals used all four.
Run the review in the same order each week:
- Tasks: mark what is done, update dates, and reassign tasks whose owner is away.
- Milestones: if the next one will slip, tell the sponsor this week.
- Dependencies: chase what is waiting, the outside ones first.
- Risks: close old ones, add new ones, and check that each response is under way.
- Scope: log new requests and the decision on each.
- Communication: send the sponsor update from the review notes.
Take the numbers for the update from the task list instead of retyping them. In It's a Plan, dashboards count the issues when you open them, and the Burnup widget projects the finish date from the pace of recent weeks.
Copy the template and start your plan
Paste this blank version into a doc or spreadsheet, fill in each section for your project, and book the first weekly review before kickoff.
PROJECT PLAN: [project name]
Plan owner: [name] Sponsor: [name] Last reviewed: [date]
1. Goal: purpose | success measures | sponsor
2. Scope: in scope | out of scope
3. Deliverables: what you hand over
4. Tasks and owners: task | owner | due date
5. Milestones: milestone | date | how it is checked
6. Dependencies: task | waits for | outside the team?
7. Risks: risk | likelihood | impact | response | owner
8. Communication: audience | what they hear | when | from
If you plan in It's a Plan, save the setup as a project template, so the next project starts with the same workflow states, issue types, labels, fields and views. Then turn each task row into an issue with an owner and a due date.
Key takeaway
A project plan answers 8 questions before work starts: goal, scope, deliverables, tasks and owners, milestones, dependencies, risks and communication. Fill in every section, even with a single line, put an out-of-scope list next to the scope, give each task one owner and a due date, and have one plan owner review the plan with the team every week so it stays tied to the work.