A burndown chart shows how much sprint work is left each day, and by day 3 or 4 you can read from its shape whether the Sprint Goal is at risk. If you don't trust the one in your tool, check the setup first: if the chart counts the wrong unit or status, its line means nothing. Set it up in four steps, then match the line to one of six shapes and act on it in the next standup.
What a sprint burndown chart shows
Agile Alliance defines the burndown chart as a graph of "the quantity of work remaining (on the vertical axis)" against the time elapsed. Ken Schwaber invented it in 2000 while working at Fidelity Investments, according to the same glossary.
A sprint burndown chart has two lines:
- The ideal line runs from the total work on the first day to zero on the last. Jira calls it the Guideline.
- The actual line shows the work left at the end of each day. Its slope, Schwaber wrote, is the velocity of work.
The 2020 Scrum Guide doesn't require the chart. It calls burn-downs, burn-ups and cumulative flows "proven useful" ways to forecast progress that "do not replace the importance of empiricism."
Which unit to burn: story points, hours or issue count
You pick the unit your burn down chart counts. Azure DevOps can burn a count of work items or a sum of story points, effort or remaining work, according to Microsoft Learn. Jira uses the estimation statistic configured for your board.
Schwaber's first version plotted hours. Mark Levison, a Certified Scrum Trainer writing for Scrum Alliance, recommends burning user stories or story points instead and updating the chart only when the team completes a story. With hours, he writes, people reduce a task "by the amount of time they worked on it, not by the amount they honestly think remains." In VersionOne's 11th State of Agile survey, run in 2016, more than half of respondents used a point system for epic estimation, and 13% used hours.
| Points | 51% |
|---|---|
| Hours | 13% |
Burn story points, or the number of stories if your team doesn't estimate. Use hours only if your team re-estimates the work left each day.
How to set up a burndown chart in 4 steps
- Fix the scope before you start. Atlassian's guide to the Jira burndown chart says that if the grey Guideline doesn't show, "the sprint may have been started before any work items were assigned to it."
- Count the work left each day. A sprint burndown "shows only one thing: How much work remains," writes Mike Cohn of Mountain Goat Software.
- Draw the ideal line from the total on the first day to zero on the last.
- Count only work that is Done. The Scrum Guide says work "cannot be considered part of an Increment unless it meets the Definition of Done." Jira counts an item as Done when you map its status to the right-most column of your board, so map only Done there. Jira also ignores story points on subtasks, so estimate the story.
How to read a burndown chart: the 6 shapes
Each morning, compare the actual line with the ideal line.
1. Flat start
The line stays at the top for the first days. Microsoft's guidance says that when the line "goes flat for a while, or remains high above the ideal trend line, the team is at risk of not meeting their sprint commitments." If you update the chart only when the team completes a story, day one can be flat. By day 3 or 4, a flat line means no item has met the Definition of Done.
What to do: meet that day and, as Microsoft advises, "reassign work, recruit more resources, or reset expectations." Finish the story closest to Done before anyone starts a new one.
2. Line going up
Schwaber warned that remaining work "will not necessarily go down," most of all early in the sprint, when the team discovers new work. Microsoft names three causes: poor estimates, new work missed in sprint planning, and scope creep the team didn't agree to. Cohn adds bugs: if the team can't fix one at once, it goes in as a new task with an estimate.
What to do: find the item someone added or re-estimated. If the team didn't agree to it, Microsoft advises moving "all nonessential sprint work to the backlog." The Scrum Guide lets you renegotiate scope with the Product Owner if no change endangers the Sprint Goal.
3. Cliff on the last day
The line stays high, then drops to zero at the end. InfoQ's 2010 summary of burndown patterns cites Hiren Doshi on two causes: the team was "lazy in updating the amount of work left," or user stories "were jettisoned" late in the sprint.
What to do: if the line is still high at mid-sprint, ask in the standup which items are finished but not moved to Done. If stories must come out, agree on it with the Product Owner at mid-sprint, while the team can still change course.
4. Steady staircase
The line drops in short steps close to the ideal, and with Levison's rule each step is a finished story. Aim for this shape.
What to do: keep stories small enough that one reaches Done every day or two. Kane Mar's seven burndown signatures, as InfoQ summarized them, include Fakey-Fakey, a line that runs straight to zero. Finished stories make steps, so if you see a straight line, ask the team how they enter the numbers.
5. Ahead of the ideal line
The actual line runs below the ideal: the team finishes items faster than planned, or someone removed items from the sprint.
What to do: check the sprint for removed items. If the scope is intact, ask the Product Owner which item to pull in next, and bring the lesson about your estimates to the next sprint planning.
6. Ending above zero
The line doesn't reach zero. InfoQ's summary quotes Doshi: "the team planning is not good since their line never touches Zero." Under the Scrum Guide, an item that misses the Definition of Done "cannot be released or even presented at the Sprint Review" and returns to the Product Backlog.
What to do: if the current slope won't reach zero, agree with the Product Owner on what to drop while there is time. At the end, don't count half-done items, and decide for each one whether it goes back to the Product Backlog or into the next sprint. In It's a Plan, unfinished issues move to the next sprint in one step when a sprint ends, and finished issues stay on the old one.
Burndown vs burnup: what a burndown hides
A burndown shows only the work left, so three things stay hidden:
- Added scope. Agile Alliance notes that burndown charts "do not indicate any changes in the scope of work." If the team finishes an item and someone adds an item of the same size that day, the line stays flat while the team works. In Jira, adding a subtask to an active sprint counts as a scope change, but Atlassian notes the chart doesn't show it if time tracking is off.
- Half-done work. Until an item meets the Definition of Done, the chart counts it the same whether it is almost finished or untouched.
- Value. A burndown can show "continued progress" but not "whether the team is working on the correct things," according to Agile Alliance.
A burnup chart covers the first gap with "a separate line for overall backlog size," in Agile Alliance's words. Use one if scope changes during the sprint or across a release, or if stakeholders ask for a finish date. On It's a Plan project dashboards, the Burnup widget projects the finish date from the pace of recent weeks.
In VersionOne's 2016 survey, 67% of respondents measured an agile project's success by velocity, 51% by iteration burndown, 38% by release burndown and 34% by a burn-up chart. Keep the burndown for daily decisions in the sprint, and add a burnup where scope changes.
| Velocity | 67% |
|---|---|
| Iteration burndown | 51% |
| Release burndown | 38% |
| Burn-up chart | 34% |
Use the burndown chart in the standup and the retrospective
The Scrum Guide sets the purpose of the 15-minute Daily Scrum as "to inspect progress toward the Sprint Goal and adapt the Sprint Backlog as necessary." Open the chart and ask:
- Which shape is the line making, and since which day?
- What changed in the sprint since yesterday? Look for added, removed or re-estimated items behind a line that rises or drops fast.
- What will we change today to protect the Sprint Goal? Reassign work, finish an item before starting another, or agree with the Product Owner on what to drop.
The Sprint Retrospective exists "to plan ways to increase quality and effectiveness." Ask the same questions about the whole sprint, then pick one change to try in the next.
Set up the chart for your next sprint
Before your next sprint planning, choose the unit, add all the work before the start and make sure only Done items count. Then run the sprint in It's a Plan as a cycle and follow its progress on the project dashboard.
Key takeaway
Set the chart up correctly before you read it: burn story points or stories, put all the work in the sprint before it starts, and count an item only when it meets your Definition of Done. Then compare the actual line with the ideal line each morning, act in the standup when the line stays flat or runs well above the ideal, and add a burnup chart when scope changes often, because a burndown hides added scope.