Agile vs Waterfall: Choose per Workstream, Not per Company

How to choose between Agile and Waterfall for each workstream: what really changes between them, one website relaunch planned both ways, a 5-question check, and how to run a hybrid with gates outside and sprints inside.

Andrii PoluosmakUpdated 9 min read

Make the Agile vs Waterfall choice for each workstream. In one project you can have work that needs a full plan up front and work that changes at every review. Score each workstream with five questions, then plan it as Waterfall, Agile, or a hybrid with stage gates outside and sprints inside.

The difference between Agile and Waterfall in one picture

Waterfall "produces a full software product at the end of a sequence of phases," the U.S. Government Accountability Office (GAO) says in a 2012 report on software development. In Agile, it says, teams work in iterations of typically one to eight weeks, and each one provides "a segment of functionality." For your own project, ask what your client could use before the whole thing is done.

Agile teams still plan. They do their initial planning for cost, scope and timing "at a high level," the GAO report says. Give an Agile workstream a date and a budget too, and detail only the next iteration.

Two timelines of equal length: Waterfall has one long plan block, three more work blocks and a single delivery at the end, while Agile has a short plan block and five small loops of work, each with its own delivery.

Agile vs Waterfall methodology: what really changes

GAO lists these differences in its report:

What changesWaterfall and traditional managementAgile
RequirementsDocumented for the complete product, then handed to technical staffIdentified in each iteration
TestingIn the final phaseIn every iteration
ProgressData and documents reviewed at set milestonesMainly software demonstrations
ClientTypically works separately from technical staffWorks often and closely with technical staff

Agile teams queue new requirements for possible inclusion in later iterations, the report says. Plan-driven methods "prefer low rates of change," Boehm and Turner write in a 2003 paper for the IEEE Agile Development Conference. Before you pick Waterfall, agree who approves a change.

Then price a late change. A 2004 NASA paper covers projects similar to a large spacecraft, a military aircraft or a small communications satellite. There, a requirements error that costs 1 unit to fix in the requirements phase costs 21 to 78 units at integration and test. Menzies and co-authors found "no evidence for the delayed issue effect," the idea that delayed issues are harder to resolve, in a 2016 study of 171 software projects. Get your own numbers: pick one likely change and ask the team what it costs in the first week and in the last.

Waterfall vs Agile project management: one relaunch, planned twice

Say you relaunch a client's website in 12 weeks. You have three workstreams: page design, a booking form and the content move.

WhenWaterfallAgile
Weeks 1 to 2Sign off requirements for every page and the formAgree rough cost, scope and dates, then rank the pages
Weeks 3 to 4Design every pageSprint 1: design, build and test the home page
Weeks 5 to 8Build every page and the formSprints 2 and 3: service pages, then the form
Weeks 9 to 10Move all the contentSprint 4: next pages, with their content
Weeks 11 to 12Test the whole site and launchSprint 5: last pages, then launch
Client first tries a pageWeek 11Week 4
New request in week 9Change the signed requirementsRank it in the queue

You launch in week 12 on both plans, so if you accept a new request, you have to push something else out. Write that trade into your plan. Disciplined teams of both kinds, Boehm and Turner write, "get their customers to agree to reducing functionality or increasing schedule in return for accommodating a new high-priority change."

Draw the Waterfall plan as a timeline and the Agile plan as a board. In It's a Plan, you can open the same issues as a Gantt chart timeline or a Kanban board.

A 5-question Waterfall vs Agile check

Boehm and Turner say to "make separate assessments" for organizations with different profiles. Do the same for each workstream:

Question0 points1 point
1. Are the requirements stable?Yes, known and agreedNo, they'll change as people see results
2. What does a late change cost?Far more than an early oneAbout the same as an early one
3. Is the date or budget fixed?Yes, and so is the scopeThe scope can give way
4. Can you ship in parts?No, only the whole is usefulYes, part by part
5. Is the client available?At milestones onlyMost days

Add up the points. With 0 or 1, plan the workstream as Waterfall, with 2 or 3 as a hybrid, and with 4 or 5 as Agile. If you score 0 on question 5, choose a hybrid instead of Agile.

If an answer isn't clear:

  • Question 1: Score 0 if the client would sign the full list today. The linear structure of Stage-Gate "may be more efficient" where markets and customer needs are "known and stable," Cooper and Sommer wrote in a 2018 paper on manufacturers.
  • Question 5: Business people and developers "must work together daily," according to the principles behind the Agile Manifesto. Ask the client for that time before you score 1.

You'd score the relaunch like this:

WorkstreamQ1Q2Q3Q4Q5TotalPlan
Page design111115Agile
Booking form100113Hybrid
Content move000101Waterfall

How to run a hybrid Agile Waterfall plan

In a hybrid you combine practices from more than one approach, Gemino, Reich and Serrador wrote on Social Science Space in 2023. Over 50 percent of the 477 cross-industry projects in their survey were hybrid.

Approach used in 477 surveyed projects

Source: Social Science Space, Agile, Traditional, and Hybrid Approaches to Project Success

Approach used in 477 surveyed projects
Hybrid (over 50%)50%
Traditional33%
Agile15%

The authors found no statistical difference among the three approaches on budget, schedule and scope or quality targets, so don't count on a hybrid alone to save money or time. Agile and hybrid projects had significantly higher stakeholder success than traditional ones, measured as the average of sponsor, client and team satisfaction. Keep all three groups close to the work, and control cost and dates at the gates:

  1. Set the gates. Gates provide "vital go/kill decision points," Cooper and Sommer write. Give each one a date, a budget limit and a decision. For the relaunch, approve page designs in week 4, the form in week 8 and launch in week 11. In It's a Plan, you can set up a gate as an initiative, a goal with a target date that turns At risk when its work falls 10% behind the time gone.
  2. Keep the outer schedule rough. Show only gates and hand-offs. The schedule Cooper and Sommer describe is like a Gantt chart but "very tentative and much higher level."
  3. Run sprints between gates. In the same paper, a stage is a series of sprints of about two to four weeks. Vary the rhythm by workstream: at Honeywell, some hardware teams work in eight-week iterations, while teams heavily integrated with software teams often do short sprints.
  4. Define a sprint result. Cooper and Sommer describe it as "merely some tangible result of the work completed in that sprint." For the form, one tested step counts.
  5. Queue the reviews. Security reviews and status briefings that sit in the backlog are addressed "concurrent with, and not after, iteration delivery," the GAO report says. Add your brand and legal reviews to the same queue.
  6. Split the audience. Show sponsors the gates and clients the sprint results. At Chamberlain, senior managers didn't have to learn Agile "because the traditional gates remained intact," Cooper and Sommer write.

A hybrid plan for a website relaunch with three gates, each with a card for a date, a budget limit and a decision, around two short sprints for page design, two for the booking form and one straight bar for the content move.

Common mistakes when you switch

  • Too little client time. Put each demo in the client's calendar now. An agency official told GAO that customers at first "did not understand the amount and pace of the time commitment for Agile."
  • The old contract. Contracts that require Waterfall artifacts and milestone reviews "may not support the frequent changes and product demonstrations in iterations," the GAO report says. Name the demos and the change rule in yours.
  • Mixed rules. Write down the method for each workstream. One agency's guidance mixed iterative and Waterfall approaches, "which staff found confusing," an official told GAO.
  • No goal line. "They're in their 39th sprint, and I'm not sure they really know where they're heading," a senior R&D executive at an optical equipment firm says in Cooper and Sommer's paper. Tie each sprint to the next gate.

Start with your next project

List the workstreams, score each one and set the gates. Then plan the project in It's a Plan: put milestones and deadlines on the outside as initiatives and run the work inside in cycles, in one project.

Key takeaway

Choose Agile or Waterfall for each workstream, not for the whole company. Score each one on stable requirements, the cost of a late change, fixed date or budget, delivery in parts, and client time. With 0 or 1 points plan it as Waterfall, with 2 or 3 as a hybrid, and with 4 or 5 as Agile, or as a hybrid if the client is available at milestones only. In a hybrid, decide at gates and work in sprints between them.

Frequently asked questions

What is the difference between Agile and Waterfall?

Waterfall plans everything first and delivers the full product at the end of a sequence of phases. Agile plans a little and delivers in parts, in iterations of typically one to eight weeks.

How do I choose between Agile and Waterfall for a workstream?

Score the workstream with five questions: are the requirements stable, what does a late change cost, is the date or budget fixed, can you ship in parts, and is the client available. With 0 or 1 points plan it as Waterfall, with 2 or 3 as a hybrid, and with 4 or 5 as Agile. If the client is available at milestones only, choose a hybrid instead of Agile.

What is a hybrid Agile Waterfall plan?

A hybrid combines practices from more than one approach. You set gates on the outside, each with a date, a budget limit and a decision, and run sprints between them.

Do Agile or hybrid projects meet their targets more often than traditional ones?

In Gemino, Reich and Serrador's survey of 477 projects, the three approaches showed no statistical difference in meeting budget, schedule and scope or quality targets. Agile and hybrid projects had significantly higher stakeholder success than traditional ones.

Andrii Poluosmak

Founder

Andrii founded It’s a Plan and leads its product and roadmap, from the open-source edition to Pro for teams. He works with the project’s contributors and the teams that run It’s a Plan.

All posts by Andrii Poluosmak

Put your next project on the board.

The open-source issue tracker you host yourself.