Resource Management: How to Balance Your Team's Time Across Projects

A step-by-step guide for team leads who share people across projects: count each person's real capacity, compare it with the work assigned for the next 4 weeks, and fix overloads by moving work or priorities.

Andrii PoluosmakUpdated 9 min read

For a team lead, resource management is one comparison: the real hours each person has against the hours of work assigned to them. In a 2008 PMI paper, James Pennypacker describes a significant disconnect: decision-makers assume there are enough resources for all projects, and often there are not. PMI, citing its 2015 Pulse of the Profession, reports that roughly 1 in 4 organizations blame project failures on scheduling problems such as task-time measurement and resource forecasting. Make the comparison for the next 4 weeks, person by person, and fix every overload by moving work or priorities before the work starts.

What is resource management in project management?

Resource management means putting the right number of people, with the right skills, on each project. Pennypacker's PMI paper on portfolio resource management states the goal as assigning the appropriate resources, in number and skills, to execute the projects in the portfolio. For a team that shares people across projects, the resource is mostly each person's hours.

The same paper splits resource management into three parts:

  1. Resource planning and estimating: how many hours of which skills the work needs, and how many hours each person has.
  2. Prioritization, allocation and scheduling: who works on what and when, and which project goes first when two need the same person.
  3. Execution, monitoring and controlling: checking that the plan still holds as the weeks pass.

Resource planning tells you whether the work fits. Allocation decides who does it and in which order. Resource leveling, which shifts task dates to remove overloads, is a separate scheduling technique for when moves alone are not enough.

In Pennypacker's 2008 research, over 74% of organizations were at level 1 or 2 of resource management maturity, without an organization-wide standard. You can apply all three parts to your own team without one.

Step 1: Count each person's real capacity

Pick a window: the next 4 weeks. For each person, take contracted hours and subtract leave and public holidays. The result is available hours.

Then set a booking limit. In a 2014 PMI paper, Narendra Shrivastava advises against assigning more than 80% of a person's availability, so the rest covers meetings, emergencies and other commitments. Keep that buffer even when a calendar looks empty: Microsoft's Work Trend Index, based on Microsoft 365 telemetry, found that 57% of meetings are ad hoc calls without a calendar invite.

Set a lower limit for people who lead. SPI Research says the same about consulting firms: senior consultants carry leadership and sales work, so their utilization target should be lower than a junior consultant's. A tech lead who runs reviews and planning needs the same allowance.

Finally, subtract work outside the projects you are balancing: a support rotation, another team's project, a recurring report. What remains is plannable hours.

Suppose a 6-person team shares two projects for the next 4 weeks. Atlas is a client portal with a fixed launch date. Beacon is an internal billing tool. Everyone is contracted for 40 hours a week, or 160 hours in the window.

PersonRoleAvailable hoursBooking limitOther commitmentsPlannable hours
MayaTech lead16060%: 96None96
LeoBackend120 (1 week of leave)80%: 96Support rotation: 1680
PriyaBackend16080%: 128Support rotation: 16112
SamFrontend16080%: 128None128
NoorDesigner16080%: 128Marketing site: 3296
JonQA16080%: 128None128

The team has 960 hours on contract and 640 plannable hours for Atlas and Beacon.

In It's a Plan, set the window up as two sprints in Cycles. Each cycle has a name and dates and lasts two weeks by default, so two cycles cover the 4 weeks.

Step 2: Map demand and find the conflicts

List every task scheduled in the window from both project plans. Give each task an owner and an hour estimate. Then add up the hours per person and compare them with plannable hours. Compare person by person, never only as a team.

PersonAtlasBeaconAssignedPlannableGap
Maya40408096+16
Leo605011080−30
Priya7060130112−18
Sam9020110128+18
Noor50308096+16
Jon404080128+48
No owner02424n/an/a

Assigned work totals 614 hours against 640 plannable hours, so the team as a whole fits. But the two backend developers are 48 hours over between them, and a 24-hour Beacon task, test data for the billing migration, has no owner.

Six rows, one per team member, each with a gray bar of assigned hours and a white marker for plannable hours; the bars of Leo and Priya run past their markers in indigo and are flagged as over the limit.

Next, count projects per person. PMI's PM Network describes a study by Steven Wheelwright in which engineers spent 65% of their time on value-added work with one project, 70% with two, and 40% when a third project was added. In the example, Noor works on three projects, and Leo and Priya each carry two projects plus support.

In task-switching experiments by Rubinstein, Meyer and Evans, described by the American Psychological Association, participants lost more time as tasks got more complex. Meyer has said that even brief mental blocks from shifting between tasks can cost as much as 40% of someone's productive time. Keep the number of projects per person low, and give each project whole days where you can.

In It's a Plan, show the window's issues in a table in Views, with columns for the assignee and the time estimate. Save it as a filtered view, so every rebalance starts from the same list. Empty assignee cells show the work with no owner.

Step 3: Resolve conflicts by moving work or priorities

Fix each overload with the cheapest move first:

  1. Move work to someone with room and the skill. No date or scope changes.
  2. Move work later, inside the window or into the next one, if its deadline allows.
  3. Change priority. When two projects need the same person in the same weeks, the person who sets priorities for both projects decides which one waits.
  4. Cut scope with the project owner when nothing else fits.

Decide in advance which work is critical. Pennypacker's PMI paper lists reallocating resources from non-critical to critical activities among the practices that high-performing organizations use significantly more than low performers.

In the example, Atlas is critical because its launch date is fixed. The team lead makes four moves:

PersonGap beforeMoveGap after
Maya+16Takes 16 hours of Beacon API work from Leo0
Leo−30Hands over the support rotation and 16 hours of Beacon work+2
Priya−1818 hours of Beacon reporting move to the next window, approved by the manager who sets priorities for both projects0
Sam+18Takes the support rotation+2
Noor+16None+16
Jon+48Takes the unowned 24-hour test data task+24

Atlas keeps every hour it had. Nobody is above the booking limit, and every task has an owner. Leave the spare hours unbooked: Jon's 24 hours absorb late testing, and Noor's 16 hours leave room for switching between three projects. Ask the marketing site owner to keep Noor's 32 hours as one full day a week instead of scattered hours.

If the moves run out and dates must change, use resource leveling to shift the schedule.

What to check every week

Capacity and demand change every week: someone is sick, a request arrives, an estimate turns out wrong. Before each week starts, check three things.

Resource utilization

Resource utilization is the share of a person's available hours that goes to assigned work. SPI Research measures billable utilization the same way, as billable hours divided by available hours. In SPI's 2026 benchmark of 509 professional services firms, firms billed 66.4% of available hours in 2025, down from 68.9% in 2024 and the lowest in SPI's surveying history. SPI sets its target at 75% or more, and it says firms that run consistently above 80% tend to struggle with burnout and retention.

Billable utilization of professional services firms

Source: SPI Research, Professional Services Benchmarks 2026

Billable utilization of professional services firms
202468.9%
202566.4%
SPI target75%
Burnout risk80%

Treat someone above 80% week after week as overloaded, even when the hours fit on paper.

Overload

Recompare assigned hours with plannable hours for every person. Gallup found that U.S. employees who strongly agree they always have too much to do are 2.2 times more likely to experience burnout very often or always. Employees who say they often or always have enough time to do all of their work are 70% less likely to experience high burnout. In Q2 2026, 27% of U.S. full-time employees told Gallup they very often or always feel burned out at work. Fix an overload in the week you find it, with the moves from Step 3.

Work with no owner

Find every task without an assignee and give it an owner before the week starts. Unowned work counts in nobody's hours, so the capacity check cannot see it. Gallup and Workhuman research with 4,439 U.S. employees found that employees who strongly agree they know what is expected of them at work are 47% less likely to experience frequent burnout.

Open the saved table from Step 2 and look for blanks in the assignee column.

Build your team's workload view before the next sprint

Put each person's assigned work on one board in It's a Plan Views and see who is overloaded before the next sprint starts. Keep the capacity table from Step 1 next to it, and move work or priorities until everyone fits under their limit.

Key takeaway

Plan no more than 80% of each person's available hours, and compare capacity with assigned work person by person for the next 4 weeks, because a team total that fits can hide overloaded people. Fix each overload with the cheapest move first: move work to someone with room, move it later, change priority, or cut scope. Then check utilization, overloads and work with no owner every week.

Frequently asked questions

How many hours a week should I plan per person?

For a 40-hour week with no leave, plan about 32 hours of project work: 80% of availability, as Shrivastava's PMI paper advises. Plan less for leads, who spend part of each week on reviews, planning and meetings.

How many projects can one person work on at once?

In the Wheelwright study described by PMI, engineers did the most value-added work with two projects and the least with three. Aim for two projects per person, and treat a third as a reason to rebalance.

How far ahead should I plan?

Plan the next 4 weeks in detail, so you see conflicts before the work starts, and re-check every week. Leave work beyond the window for the next plan instead of estimating it now.

Andrii Poluosmak

Founder

Andrii founded It’s a Plan and leads its product and roadmap, from the open-source edition to Pro for teams. He works with the project’s contributors and the teams that run It’s a Plan.

All posts by Andrii Poluosmak

Put your next project on the board.

The open-source issue tracker you host yourself.