It’s a Plan

Critical Path Project Management: A Worked Example You Can Copy

Work through an eight-task example to find the critical path: run the forward and backward pass, calculate float for each task, and choose a response when a critical task is late.

Andrii PoluosmakUpdated 8 min read

With critical path project management, you can see which tasks set your deadline and which can wait. List your tasks and dependencies, calculate the earliest and latest dates for each task, and protect the ones with no float.

Find your critical path before you promise a date. In Wellingtone's 2026 State of Project Management survey, 36% of organizations said they mostly or always complete projects on time.

What is critical path in project management?

The critical path is the longest chain of dependent tasks. In its Schedule Assessment Guide for government programs, the U.S. Government Accountability Office (GAO) says this path "defines the program's earliest completion date or minimum duration." With no date constraints, the guide says, a delay to a critical task moves the forecast finish day for day.

A long duration alone doesn't make a task critical, the guide adds. Kramer and Jenkins note in a 2006 PMI paper that a schedule can have more than one critical path, so check every chain.

Critical path project management example: the setup

In this critical path method example, you're planning a one-day customer event. For each task, write down the duration in working days and the tasks that must finish first.

TaskDaysDepends on
A. Agree scope and budget3none
B. Book the venue5A
C. Confirm the speakers7A
D. Publish the event page4B, C
E. Prepare the talks8C
F. Invite guests10D
G. Print the handouts4E
H. Rehearse and set up2F, G

Each link is finish-to-start, which Kramer and Jenkins define as the first task being 100% complete before the next can start. D waits for B and C because the event page lists the venue and the speakers.

Draw the tasks as boxes joined by arrows. In It's a Plan Notes, you can do this with sticky notes connected by lines.

How to calculate critical path: forward and backward pass

You get "90% of the value" by drawing the network and calculating early times, late times and float, the developers of the critical path method (CPM) say in PMI's Origins of CPM. Use the formulas from Kramer and Jenkins:

  • Early start (ES) = highest EF of the tasks directly before it
  • Early finish (EF) = ES + duration
  • Late finish (LF) = lowest LS of the tasks directly after it
  • Late start (LS) = LF − duration

Forward pass: earliest dates

Start at 0, the end of day zero, and work forward.

  1. A runs from 0 to 3, B from 3 to 8 and C from 3 to 10.
  2. D waits for B and C. It starts at the later finish, 10, and ends at 14.
  3. E runs from 10 to 18, F from 14 to 24 and G from 18 to 22.
  4. H waits for F and G, so it runs from 24 to 26.

The last early finish is the project duration: 26 working days.

Backward pass: latest dates

Set H's late finish to 26 and work back.

  1. H must start by 24, so F and G must finish by 24. That means starting F by 14 and G by 20.
  2. D must finish by 14 and start by 10. E must finish by 20 and start by 12.
  3. C feeds D (late start 10) and E (late start 12). Take the lower number, so C must finish by 10 and start by 3.
  4. B must finish by 10 and start by 5. A feeds B (5) and C (3), so it must finish by 3 and start by 0.
TaskESEFLSLFTotal floatFree float
A030300
B3851022
C31031000
D1014101400
E1018122020
F1424142400
G1822202422
H2426242600

Float in project management: which tasks can slip

Total float is how long a task can slip before the finish date moves. Free float is the part of it you can use before the next task moves. Kramer and Jenkins use these formulas:

  • Total float = LS − ES
  • Free float = lowest ES of the next tasks − EF

The tasks with zero total float form the critical path: A, C, D, F, H. Add up their durations and you get the project duration, as Kramer and Jenkins say you should: 3 + 7 + 4 + 10 + 2 = 26. B, E and G can each slip by 2 days. If E slips, G moves too, because E has no free float.

Network diagram of tasks A to H with the critical path A, C, D, F, H highlighted in indigo, and B, E and G each labelled 2 days float.

Any task along a sequence can use its float, the GAO guide says, so count float once per chain: E and G have 2 days between them. Use float to move people from tasks that can slip to tasks that can't. Watch B, E and G too. For a brief schedule, the guide gives a 5-day slip as an example near-critical threshold.

Record the float next to each task. In It's a Plan Views, you can see a custom field for float as a column.

When a critical task is late

Suppose it's the end of day 8. You have booked the venue, but confirming the speakers will take 9 days instead of 7. C is critical, so the finish moves to day 28. You can bring it back to day 26 with any of these responses:

ResponseChangeNew critical path
CrashAdd a person to F, so it takes 8 daysA, C, D, F, H and A, C, E, G, H
Fast-trackStart F 2 days before D endsThe same two paths
Re-sequenceD stops waiting for CA, C, E, G, H

Crash a task when you can spend money to shorten it. Origins of CPM advises starting with the critical job that raises direct cost at the lowest rate, and warns that other jobs become critical too. Cut F to 7 days here and you gain nothing more, because A, C, E, G, H still takes 26. Subtract handover and training time from the days you expect to gain. In a hypothetical PM Network example by Patricia Lira Mogollón, a senior hire nets 20 days and a junior hire none.

Net days gained in a hypothetical crashing example

Source: PMI, PM Network, Mission critical

Net days gained in a hypothetical crashing example
New tool30
Senior hire20
Junior hire0

Fast-track when different teams can overlap dependent tasks. Fast-tracking almost always raises risk and may cause rework, says Patrick Weaver of Mosaic Project Services in PMI's On the right track. Citing Weaver, the piece limits overlap to different teams and excludes testing. Overlap D and F only if two teams do them, and keep the rehearsal last.

Re-sequence tasks if a dependency is your choice. Managers may change the sequence of activities after a status update, the GAO guide says. Here you can publish the page with the venue and add the speakers later, so D runs from 8 to 12 and F from 12 to 22. Both gain 2 days of float, and the critical path moves to E and G.

Before and after network diagrams: once the link from C to D is removed, the critical path moves from A, C, D, F, H to A, C, E, G, H.

Keep the critical path current

In the 1957 to 1958 Repauno test described in Origins of CPM, some 30% of the original design and equipment delivery dates had changed by the first update, within two months. Record each dependency as a link in your project tool, and check the path every week:

  1. Task owners report progress to one scheduler. The GAO guide assigns this role to someone trained and experienced in CPM scheduling.
  2. The scheduler checks that finished work is in the past and unfinished work is in the future.
  3. Then the scheduler reruns both passes and tells the team which tasks became critical.

If you report status weekly, the GAO guide says to track progress daily.

Run it on your project

Replace the eight tasks with yours and run both passes. Then link dependent tasks as blocking in your project tool. Mark the zero-float tasks and, in It's a Plan, save a filter for them as a view, so the chain that sets your deadline is on one board.

Key takeaway

The critical path is the longest chain of dependent tasks, and it sets the earliest finish date. List your tasks and dependencies, run the forward and backward pass, and calculate total float as late start minus early start. A task with zero float can't slip without delaying the finish. When a critical task is late, crash, fast-track or re-sequence, then recalculate.

Frequently asked questions

What is the critical path in project management?

The critical path is the longest chain of dependent tasks in a project. It sets the earliest finish date. A schedule can have more than one critical path, so check every chain.

How do you calculate the critical path?

List each task with its duration and the tasks that must finish first. Run a forward pass to get the early start and early finish of each task, then a backward pass to get the late finish and late start. The tasks with zero total float form the critical path.

What is the difference between total float and free float?

Total float is how long a task can slip before the finish date moves. It is late start minus early start. Free float is the part of it you can use before the next task moves. It is the lowest early start of the next tasks minus the early finish of the task.

What can you do when a critical task is late?

You can crash a task by spending money to shorten it, fast-track by overlapping dependent tasks, or re-sequence tasks if a dependency is your choice. Then recalculate, because the critical path can move.

Andrii Poluosmak

Founder

Andrii founded It’s a Plan and leads its product and roadmap, from the open-source edition to Pro for teams. He works with the project’s contributors and the teams that run It’s a Plan.

All posts by Andrii Poluosmak

Put your next project on the board.

The open-source issue tracker you host yourself.