A copyable project proposal template with a worked method for filling it in, a one-page version and an approval checklist. It also shows how to connect deliverables to acceptance, assumptions and costs, and how to carry approved commitments into the project plan.

Andrii PoluosmakUpdated 16 min read

Use a project proposal template to ask for a specific decision: what problem needs attention, what work you propose, what it will cost, and what the approver would authorize. Write the request first, then build the scope, deliverables, acceptance criteria, assumptions, and budget around it.

Check when you will receive the required inputs before committing to a delivery date. Check the included work before quoting a price. As a project lead, consultant, or agency manager, put those conditions in the proposal so the approver can review them before accepting the commitment.

Choose a short or detailed project proposal template

Decide what you need the reader to authorize: investigation, detailed planning, a purchase, or delivery. Put that request at the top of your working draft, even if you write the executive summary last.

HM Treasury’s 2026 Green Book says proposal-development effort should correspond to scale, cost, complexity, and risk. Apply that principle when choosing how much detail to include, while following your organization’s own approval requirements.

Use a simple project proposal template if you can explain the problem, boundaries, resources, risks, and requested decision without leaving essential conditions for a separate conversation. Keep enough detail for the reader to judge the commitment.

Choose a detailed version if the approver needs to compare options, review uncertain estimates, or authorize work across several teams and dependencies. Put the decision summary first and the supporting detail underneath it.

Shorten the background before cutting exclusions, assumptions, or conditions attached to the price and deadline.

What belongs in a one-page version?

For a one page project proposal template, use these headings:

  • Decision requested: What should the approver authorize, and by when?
  • Problem and evidence: What needs to change, and what supports that assessment?
  • Proposed work: What will you deliver, and what is excluded?
  • Acceptance: How will the recipient confirm the work meets the requirement?
  • Resources and timing: Who is needed, what will it cost, and what controls the dates?
  • Conditions: Which assumptions, dependencies, and risks affect the commitment?
  • Approval: Who decides, what version are they reviewing, and what happens next?

Expand the document if you cannot fit the answers on a legible page. Mention essential conditions in the decision summary, even if you explain them in an appendix.

Separate the proposal from the delivery plan

Use the proposal to request authorization for a defined course of action. In the delivery plan, describe how you will organize, assign, schedule, and control the authorized work. Follow your organization’s document names and sequence.

The Association for Project Management describes a business case as an evaluation of alternative options through benefits, costs, and risks. Include that reasoning in your approval material, or point the approver to the business case your process requires.

For discovery work, request permission to investigate and return with a better estimate. Keep that request separate from permission to deliver the final solution.

Copyable project proposal template

Copy the sections below and replace the prompts with your project information. Before deleting a prompt, check whether the approver needs the answer to make the decision.

If you need a project proposal template Word can hold, paste the text into a new document and apply heading styles. Use a consistent format for deliverables and cost records, with conditions beside the commitments they qualify.

Project details and decision requested

Project title: [Use a name that identifies the proposed change.]

Proposal owner: [Name and role responsible for maintaining the proposal.]

Version and review date: [Identify the exact document being considered.]

Decision owner: [Name the person or body authorized to approve this request.]

Decision requested: [Authorize discovery, planning, purchase, delivery, or another explicit action.]

Decision needed by: [State the date and explain any consequence of a later decision.]

Authority requested: [State the spending limit, resource allocation, or other permission required.]

Replace “approve the project” with the work you want to undertake and the authority you need. Give the approver a request they can accept, reject, or return for a specific revision.

Problem, evidence, and intended outcome

Current problem: [Describe the condition affecting the team, customer, or organization.]

Supporting evidence: [Identify the record, observation, research, or measurement supporting the problem statement, including its period and owner.]

Consequence of continuing: [Explain what is expected if current arrangements continue.]

Intended outcome: [Describe the change sought, distinguishing a target from a guaranteed result.]

Benefit measurement: [Name the measure, baseline, measurement owner, and review point.]

If you have no baseline, include collecting one in the proposed work. Leave improvement percentages out until you can support them.

Options and recommended approach

Options considered: [Include continuing current arrangements and any realistic alternatives.]

Recommended approach: [Describe the work you propose.]

Reason for the recommendation: [Compare the options against the decision criteria that matter.]

Conditions that would change the recommendation: [Identify missing information or assumptions that could alter the choice.]

Include the implementation effort for your preferred option and compare it with realistic alternatives.

Scope, deliverables, and exclusions

Complete a record for each deliverable:

Deliverable ID and name: [Give the output a stable identifier.]

Included work: [Describe what the team will produce and the boundaries of that work.]

Acceptance criteria: [State the observable conditions the deliverable must satisfy.]

Acceptance method and reviewer: [Name the inspection, demonstration, test, or analysis and the person responsible.]

Inputs and dependencies: [Identify what must be available, from whom, and by when.]

Exclusions: [State adjacent work that the proposal does not authorize.]

Keep the names and identifiers consistent in the schedule and cost estimate. If you add a deliverable to the executive summary, add its effort, acceptance conditions, and owner to the detailed scope.

Resources, schedule, and cost

Delivery roles: [List the roles needed and their responsibilities.]

Availability: [State the allocation requested and who confirms it.]

Milestones: [List the meaningful review, delivery, and acceptance points.]

Schedule basis: [Explain whether dates are fixed, estimated, or dependent on an event.]

Cost basis: [Show effort multiplied by the applicable rate, plus identified external costs.]

Contingency: [Explain the uncertainty covered, the amount requested, and who may authorize its use.]

Total authority requested: [Reconcile the amount with the opening decision request.]

Commercial conditions: [Where relevant, identify payment terms, taxes, expenses, and the documents controlling them.]

APM’s planning guidance describes bottom-up estimating as estimating time and cost for individual components of work. Estimate the deliverables and management activities, then check that you have covered the proposed scope.

Assumptions, risks, and approval record

Assumptions: [State what you are treating as true in the proposal, who will validate it, and the validation deadline.]

Risks: [Describe uncertain events, their consequences, the response, and the responsible owner.]

Change route: [Explain how requests affecting scope, timing, cost, or acceptance will be assessed and decided.]

Approval record: [Record the decision, approver, date, proposal version, conditions, and limits.]

Next authorized action: [State what may begin after approval and what remains unauthorized.]

HM Treasury’s Green Book calls for assumptions to be transparent and agreed by decision makers. Put the assumptions that affect the decision in the approval summary as well as the supporting register.

Work through your own project proposal example

Choose a project you are preparing for approval and complete the template from its records. Start with a specific deliverable and work through its acceptance conditions, required inputs, effort, and requested authority. Repeat for the remaining scope.

Enter people’s confirmed availability, applicable rates, dates, and approval limits before submitting the proposal.

Decision and problem

Name the project. Use the name your stakeholders recognize and state the change you want to make. Identify the proposal owner and the person responsible for the decision.

Write the authorization request. Describe the work you want permission to begin and the resource allocation or spending authority you need. Distinguish permission to investigate or plan from permission to deliver.

Describe the problem from project records. Identify the affected work or recipient, the current condition, and the supporting record. Include the measurement period and ask the record owner to confirm details you cannot establish.

Define the intended outcome. State the change you want to achieve and how you intend to assess it. Keep proposed targets separate from measured results.

Prepare the decision summary. Bring the request, problem, proposed approach, and cost limit together. Include the conditions the approver needs to review before deciding.

Compare the request with the problem statement. Check that you have explained how the proposed work addresses the condition you want to change.

Approach and deliverables

Compare the available approaches. Include continuing current arrangements. Record the reasons for your recommendation, the assumptions behind it, and the preparation and review effort required.

List the actual deliverables. Use the names from the scope you intend to submit. Give each an identifier and describe the included work and intended recipient. Put adjacent work you are not requesting authorization for in the exclusions list.

Specify acceptance for each output. Agree observable conditions with the recipient and name the reviewer. Choose the inspection, demonstration, test, or analysis you will use and include its preparation in the estimate.

Record required inputs. Name the person supplying each input and when the team needs it. Confirm these commitments with the people involved before using them to support a delivery date.

Prepare for the handoff. Retain the approved scope, exclusions, and approval conditions when you create delivery work records. Connect each deliverable to the tasks needed to produce and verify it.

Keep scope questions on a decision list until the authorized person resolves them. Wait for authorization before starting the tasks you have listed.

Schedule and dependencies

Establish the start conditions. Identify the approval, inputs, and resource availability you need to begin. Name the person who will check those conditions and record the outcome.

Schedule preparation and delivery. Arrange the work around the required inputs. Include review points before commitments that depend on the reviewer’s decision.

Allow for acceptance. Agree review turnaround with the designated reviewer and include time for corrections within scope. Name the person who will decide whether the output meets the acceptance criteria.

Record timing assumptions. Separate confirmed availability from assumptions you need to validate. Set a confirmation deadline and identify which commitment you must revisit if the assumption proves wrong.

Check the finish condition. Describe the acceptance or handover decision needed to close the work. Keep unresolved requests for additional scope separate from acceptance of the authorized deliverables.

Check inputs and availability before entering calendar dates. For a fixed finish date, work backward to confirm that you have allowed enough time for preparation and review.

Cost and approval

Calculate work costs. Multiply the estimated hours for each role or activity by its applicable rate. Follow the scope boundaries in the deliverable records and include planned review effort.

Add external costs. Identify the purchases or services required within scope. Record conditions affecting the amount and who will confirm them before you commit to spending.

Explain contingency. Name the uncertainty you intend to cover, the amount requested, and who may authorize its use. Show the allowance in the total.

Reconcile the request. Add work costs, external costs, and requested contingency. Resolve differences between that total and the spending limit in the decision summary before submission.

Keep benefits separate. If you request approval based on financial benefits, attach the baseline, calculation, measurement owner, and assumptions. Do not record a saving for completing a deliverable alone.

Complete the approval record. Ask the authorized decision maker to record the outcome against the proposal version, including resource and cost limits and any conditions. State which action may begin and which actions need a further decision.

Before submitting, name the accountable people, complete the estimate, and agree the dates. Obtain a spending limit before committing funds.

Connect deliverables to acceptance, assumptions, and costs

For each deliverable, identify the problem you intend to address, how the reviewer will accept the output, and the resources and conditions you need to deliver it.

APM’s requirements-management guidance says requirements should be consistent, verifiable, and traceable from the original need through the plan to delivery. Review each deliverable against those three tests before requesting approval.

Take a deliverable from your scope and trace it through the proposal. Confirm that you have used its name in the schedule and cost estimate. Identify the acceptance reviewer, the required input, and the person supplying it. Include the effort to produce and verify the output in the estimate.

Repeat for the remaining deliverables. Question any deliverable you cannot connect to an approved need. If you have allocated no time for a required review, revise the estimate or obtain a different commitment.

A highlighted deliverable card is linked to three rows for acceptance, required input and effort, which all lead to one delivery work item with an owner.

Keep output acceptance separate from benefit measurement

HM Treasury’s Green Book says the explanation connecting proposed work to intended outcomes should rest on evidence and careful reasoning. State the expected benefit separately from the conditions for accepting the deliverable.

Write down what the reviewer must inspect, demonstrate, test, or analyze before accepting the output. Record the intended business improvement and its measurement point in the benefits section. Define the improvement and arrange to measure it before making it an acceptance condition.

Distinguish what the team controls from what the recipient checks and what someone will measure later. Name the person responsible for each.

Test the assumption that matters most

HM Treasury’s Green Book recommends sensitivity analysis to examine how changes in key assumptions affect appraisal results. Apply a proportionate version by changing a consequential input in your estimate and checking the effect.

Review preparation effort, review turnaround, external costs, and availability. Identify which change would make the budget or date unacceptable, and show the approver what you need to confirm before committing.

Choose a response: confirm the input, allow more time, request reduced scope, or return for a revised decision. Explain the uncertainty you intend to cover with contingency.

Run the approval checklist before sending

Read the proposal as an approver who missed the working discussions. Check that you have included the conditions they need to judge the request.

Evidence and benefits

  • The problem statement identifies the supporting records or measurements.
  • Proposed targets are distinguished from observed results.
  • Benefits have a measurement owner and review point.
  • Financial benefits show their calculation and assumptions.
  • Continuing current arrangements is described fairly.

Remove unsupported claims. If you need a baseline, request the work to collect it before committing to an improvement.

Scope and acceptance

  • Deliverables have consistent names throughout the document.
  • Exclusions identify adjacent work that readers might otherwise expect.
  • Acceptance criteria can be checked through a named method.
  • A reviewer is responsible for each acceptance decision.
  • Inputs and dependencies are attached to the deliverables they affect.
  • Review and correction effort is included in the proposed work.

Compare the scope with the executive summary and correct any promise that exceeds the detailed scope before asking for approval.

Cost and schedule

  • The estimate covers all included deliverables and management work.
  • Rate, quantity, and external-cost assumptions are visible.
  • Totals agree with the opening request.
  • Contingency has a stated purpose and authorization route.
  • Resource availability supports the schedule.
  • Dates distinguish fixed commitments from conditional estimates.

Check the arithmetic, then compare the cost entries with the proposed work. Look for required activities you have omitted from the total.

Authority and decision

  • The named approver has authority for the requested decision.
  • The proposal identifies the version under review.
  • Approval states what can start and what cannot.
  • Conditions have owners and a way to confirm they are met.
  • The decision record captures limits and required follow-up.

APM assigns business-case ownership to the sponsor in its guidance. Confirm who can authorize purchases, resource allocations, and contractual commitments in your organization before sending those requests to the sponsor.

Transfer approved commitments into the project plan

Transfer the approved scope and conditions into the delivery plan before assigning the work. Keep deliverable identifiers so the team can trace tasks back to what the approver authorized.

APM’s planning guidance says an agreed management plan becomes a baseline maintained through change control. Record the accepted scope, schedule, resources, acceptance arrangements, and unresolved conditions in that plan.

Use this handoff sequence:

  1. Identify the approved version. Keep the decision and its conditions with the proposal.
  2. Transfer the deliverables. Retain scope boundaries and exclusions alongside the planned work.
  3. Assign responsibility. Name who produces each output, who supplies inputs, and who accepts it.
  4. Schedule verification. Include reviews, tests, corrections, and dependency checks.
  5. Reconcile the estimate. Confirm that planned effort and external costs fit the authorized limits.
  6. Review open conditions. Do not start restricted work before the required decision or input arrives.

Keep the source wording accessible while creating tasks. In It’s a Plan, Docs lets you select document text and turn it into an issue. Create an issue from the approved commitment, then add its owner and acceptance details.

Decide changes before updating commitments

APM’s change-control guidance calls for evaluating proposed changes and recommending approval, rejection, or deferral to the sponsor or governance body. Record the request and assess its effects before treating it as agreed work.

Capture the requested change, its reason, affected deliverables, and impact on cost, timing, resources, risks, and acceptance. Name the decision maker and record the outcome.

APM also says the plan is updated when a change is approved. After approval, update the affected commitments together, including the acceptance criteria and estimate. Check the task against the revised baseline.

Put the proposal in front of the right approver

Copy the template, replace its prompts with project evidence, and check that scope, costs, assumptions, and acceptance describe the same commitment. Ask the approver to review those conditions and record the exact decision requested.

If your team keeps its planning material in It’s a Plan, put the proposal in Docs beside the delivery work. After approval, turn the authorized commitments into issues and keep unresolved decisions separate from permission to begin.

Key takeaway

A project proposal asks for one specific decision. Match its detail to the cost, complexity and risk of that decision. Give each deliverable an acceptance method, an owner and its assumptions. Keep estimated costs, spending authority and expected benefits apart. Record what the approval authorizes, then carry those commitments into the delivery plan and change them only through change control.

Andrii Poluosmak

Founder

Andrii founded It’s a Plan and leads its product and roadmap, from the open-source edition to Pro for teams. He works with the project’s contributors and the teams that run It’s a Plan.

All posts by Andrii Poluosmak

Put your next project on the board.

The open-source issue tracker you host yourself.