It’s a Plan

What a Public-Sector Project Charter Should Carry Through a Leadership Change

When a sponsor or director changes on a public-sector project, the charter shows what still stands. This guide shows how to sort commitments, separate confirmed from provisional funding, flag exposed milestones and give the new leader a one-page handover brief.

Andrii PoluosmakUpdated 7 min read

The PMBOK Guide, third edition, quoted in a 2005 PMI paper by Alex S. Brown, defines a project charter as "a document issued by the project initiator or sponsor that formally authorizes the existence of a project." In a public-sector program, the leader who issued that authority can move on before the work ends. When a sponsor, director or senior responsible owner changes, go back to the charter and sort your commitments: what remains authorized, what the incoming leader must reconfirm, and who decides each point. Give the new leader that list on one page.

On November 16, 2026, Maryland's Department of Housing and Community Development announced that Christine McPherson had been promoted to Director of Maryland Revitalization Programs. She succeeds Kevin Baynes, who is retiring after nearly three decades with the department. Under his management, more than $336 million in State Revitalization Program funding was awarded to support 996 community projects and initiatives. McPherson will work through grants, technical assistance and partnerships with local governments and community organizations. The same announcement named Dr. Liz Karberg the division's new Director of Policy, Planning, and Program Development. Every grant condition and partner agreement in a portfolio like that has to reach the new leaders in a form they can act on.

Why a project charter needs a check after every leadership change

In PMI's 2021 Pulse of the Profession survey of 3,950 project professionals, 41% selected a change in the organization's priorities as a primary cause of project failure, more than any other cause. Plan for that risk at every handover.

The UK National Audit Office reported in 2013 that senior responsible owners (SROs) for major defence projects had typically moved post every two to three years. In its 2023 lessons on resetting major programmes, the NAO lists a high turnover of senior leaders as contributing to a lack of clarity and confused objectives. Between 2014 and 2019, the Home Office appointed four SROs and three programme directors for its Digital Services at the Border programme.

An Association for Project Management study published in 2026 interviewed ten experts on national-level UK and Scottish government projects. They named shifting priorities, unclear funding, weak leadership and frequent role changes among the factors that affect the success of multi-agent projects. The study recommends leadership continuity and funding tied to milestones.

Don't wait for your organization to plan the handover. In the MissionSquare Research Institute's 2026 survey of 606 state and local government HR managers, 53% said their organization has no formal succession planning process.

Brown writes that when a new project manager joins a project already underway, reconfirming the existing charter or writing a new one is a great way to establish credibility. Run the same check when the sponsor changes. He also warns that the change requests may have become the new charter, so read the approved ones alongside the original document.

Preserve shared objectives, agency commitments and decision rights

Start with what a new leader can't rebuild from memory:

  • Shared objectives. The outcome each agency agreed to, in the wording it signed.
  • Agency commitments. What each partner delivers, by when, and under which agreement or grant.
  • Decision rights. Who can reschedule, change the project scope, release funds or stop the work, and the limit on each.

Write each decision right with its limit. A Department for Transport appointment letter for the SRO of the South West route capacity programme lets the SRO agree project rescheduling as long as the project stays within the budgets signed off in the 2015 Spending Round. Changes beyond that go to the Director General, the Accounting Officer and the DfT Board. A Home Office letter for the nuclear security portfolio says proposed scope changes that affect intent or benefits must be escalated to the investment committee.

Keep policy decisions apart from delivery decisions. The same Home Office letter says it remains for the Minister to account for any relevant policy decisions and their development. Mark each open decision as policy or delivery, so the incoming leader knows which ones need a political answer and which need an executive one.

Keep the charter as a page in It's a Plan Docs, the team wiki linked to issues. Select a commitment in the text and choose Create work item: the commitment becomes an issue linked to the page. Assign it to the agency lead who owns it.

Separate confirmed funding from provisional funding

Give the incoming leader approved money and expected spend as two figures. The South West route letter puts the total forecast upgrade cost for the infrastructure elements at £640m, while the current approved expenditure is £510m. The nuclear security letter says funding authorisations will be confirmed separately and kept under review in the light of delivery progress.

Record each funding line with these fields:

FieldWhat to write
Funding lineThe source, such as an appropriation, a grant or a partner contribution
StatusConfirmed or provisional
AmountThe approved amount, and the forecast if it differs
ConditionsThe milestones, reviews or matching funds the money depends on
Who can change itThe person or body that can release, cut or extend it

Tie each provisional line to the milestone that unlocks it, as the APM study recommends for funding. Brown adds that when the first charter authorizes work only up to a set budget, the project manager must get a new charter from the sponsor before that ceiling is hit. If the project will reach that ceiling in the new leader's first months, put it at the top of the handover.

Flag milestones and partner commitments exposed to a change in priorities

The NAO names financial pressures and political changes among the external factors that may mean a programme needs to reset. Ask three questions about each milestone and partner commitment:

  1. Does it depend on a priority the outgoing leader set?
  2. Does it depend on provisional funding?
  3. Does a partner need a decision from your side before it can act?

A yes to any of them means the item is exposed. Mark it on your project roadmap, so partners can see which dates wait on a reconfirmation.

In It's a Plan, give each exposed commitment a label and save a filtered table in Views, so you and the new leader review the same list.

Build the one-page handover brief

A charter can be as short as part of a single page, Brown writes, so long as it clearly provides authority to the project and project manager. Keep the handover brief to one page too. A November 2026 ProjectManagement.com webinar on project visualization argues for shifting status reporting from activity updates to decision-focused conversations. Build the brief around decisions, in three blocks:

  • Remains authorized. The objectives, commitments and funding the incoming leader can let run.
  • Needs reconfirmation. Each exposed item, with the decision required and the date it is needed by.
  • Who decides. The person or body for each decision, with the limit of their authority.

Date the brief and state the baseline it describes. The South West route letter records the programme's status as the agreed position when the new SRO assumes formal ownership. Ask the incoming leader to sign off your baseline the same way, so you measure later changes from it. Keep the detail in the project management plan and point to it from each line.

A one-page handover brief under a Baseline line, with three columns: Remains authorized with green-marked rows, Needs reconfirmation highlighted with two rows flagged orange as exposed, and Who decides with an initials avatar beside each row.

Use any overlap between the two leaders. Under the nuclear security letter, an SRO who is allowed to leave must give three months' notice, including a month working alongside the replacement SRO. Walk through the brief together during the overlap. With no overlap, send the brief before the new leader's first review.

Mark the first commitment to reconfirm

Review one live charter with a partner agency and mark the first commitment a new leader would need to reconfirm. Open the charter as a page in It's a Plan Docs, turn that commitment into a work item, and assign it to the person who will put it to the new leader.

Key takeaway

When the leader who authorized a public-sector project changes, check the charter and its approved changes. Then give the incoming leader one page that shows what remains authorized, what needs reconfirmation and who decides each point, with confirmed and provisional funding listed separately.

Frequently asked questions

Is a project charter still valid after the sponsor who signed it leaves?

Ask the incoming leader to reconfirm it at the first review, and record the date. Until then, work within the limits the charter and the approved change requests already set.

Andrii Poluosmak

Founder

Andrii founded It’s a Plan and leads its product and roadmap, from the open-source edition to Pro for teams. He works with the project’s contributors and the teams that run It’s a Plan.